Finland's TVO challenges approval of Areva bailout

Arab Today, arab today

Arab Today, arab today Finland's TVO challenges approval of Areva bailout

he European Pressurised Reactor (EPR) reactor at Olkiluoto, or OL3, is now expected to open nine years late in 2018
Paris - Arab Today

Finnish utility TVO said Wednesday it would appeal the EU's approval of a bailout of Areva, saying it did not provide adequate guarantees the French nuclear giant would be able to complete construction of a reactor in Finland.

Areva, together with German engineering group Siemens, has been building in Finland since 2005 what was meant to be a showcase of next-generation nuclear power, but which has instead showcased the industry's chronic delays and cost overruns.

The European Pressurised Reactor (EPR) reactor at Olkiluoto, or OL3, is now expected to open nine years late in 2018.

The mounting bill for the reactor, plus the crippling blow to the sector's prospects dealt by the 2011 Fukushima disaster in Japan, led the French government in 2015 to launch a restructuring of the firm that would see parts of it split up and sold off.

In January, the European Commission gave the go-ahead to the French government to invest 4.5 billion euros to salvage its operations, which it did in July.

"TVO is not opposed in principle to the intervention by the French State in favour of the Areva Group, provided that TVO's needs for OL3 EPR are fully taken into account, which is currently not the case," the Finnish company said in a statement.

It said the French government's bailout of Areva "does not provide sufficient guarantees to TVO that the necessary financial, technical and human resources are to be made available for the OL3 EPR project."

TVO added its concern that the bailout "does not ensure that Areva is able to meet all current and future liabilities during the last phases of project completion and until the end of the guarantee period."

Areva said the TVO challenge at the General Court of the European Union wouldn't affect the calendar for finishing up Olkiluoto or its restructuring.

"The restructuring of Areva is nearly complete", an Areva spokesman told AFP, adding that "TVO's action won't change the timing."

The restructuring left Areva with the obligations to complete the Olkiluoto reactor, while its reactor and nuclear fuel businesses were sold off or transferred into new companies.

Areva and TVO are claiming billions of euros in damages from one another in arbitration proceedings.

Source: AFP

arabstoday
arabstoday

Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

finlands tvo challenges approval of areva bailout finlands tvo challenges approval of areva bailout

 



Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

finlands tvo challenges approval of areva bailout finlands tvo challenges approval of areva bailout

 



GMT 04:51 2016 Thursday ,29 December

Sisi inaugurates Nasr Floating Bridge in Port Said city

GMT 08:53 2017 Thursday ,02 November

Muslim countries push UN to speak out on Myanmar abuses

GMT 14:26 2017 Saturday ,21 October

Jazeera launches new livery, cabins, crew uniforms

GMT 21:11 2011 Friday ,13 May

How to treat a cold

GMT 09:10 2015 Saturday ,03 January

The Perfume Shop reveals January & February

GMT 18:21 2017 Sunday ,08 October

Dangerous Takfiri element arrested

GMT 13:27 2017 Saturday ,14 January

Kardashian heist charged in Paris

GMT 05:09 2017 Wednesday ,25 October

Austria far-right set for coalition talks

GMT 08:10 2017 Thursday ,27 April

Abu Dhabi International Book Fair launched

GMT 23:37 2017 Wednesday ,15 November

Foxconn profit tumbles after iPhone X production hurdles

GMT 10:42 2018 Monday ,03 December

Abbas arrives in Rome to counteract Israeli policy

GMT 12:48 2017 Thursday ,23 February

Iraq forces attack ISheld Mosul airport

GMT 09:25 2018 Monday ,15 January

Mark Wahlberg donates $1.5 million

GMT 08:16 2018 Friday ,12 January

Sit-ins, APCs no solution to issues: PM

GMT 05:40 2018 Wednesday ,10 January

SkinSincere appoints Soapbox PR

GMT 13:02 2018 Monday ,01 January

Berlin truck attack suspect shot dead

GMT 04:48 2017 Saturday ,30 December

Grieving Afghans end deadly year

GMT 05:14 2017 Monday ,27 February

New Saudi stock market opens with gains of 20%

GMT 16:09 2017 Saturday ,15 April

Tanzania gunmen kill 8 police in restive region

GMT 05:08 2017 Sunday ,12 March

Bangladeshis top expat workers in Oman
Arab Today, arab today
 
 Arab Today Facebook,arab today facebook  Arab Today Twitter,arab today twitter Arab Today Rss,arab today rss  Arab Today Youtube,arab today youtube  Arab Today Youtube,arab today youtube

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

arabstoday arabstoday arabstoday arabstoday
arabstoday arabstoday arabstoday
arabstoday
بناية النخيل - رأس النبع _ خلف السفارة الفرنسية _بيروت - لبنان
arabstoday, Arabstoday, Arabstoday