174m cubic meters dug at new suez canal project
Last Updated : GMT 06:49:16
Arab Today, arab today
Arab Today, arab today
Last Updated : GMT 06:49:16
Arab Today, arab today

174m cubic meters dug at new Suez Canal project

Arab Today, arab today

Arab Today, arab today 174m cubic meters dug at new Suez Canal project

New Suez Canal
Ismailia - MENA

After 154 days of starting work on the new Suez Canal Project, 174 million cubic meters of dry land dredging have been completed, project supervisor Kamal el-Waziri said.
The total number of workers on site is nearly 23,000 (engineers, technicians, workers and drivers) through 84 companies in addition to two battalions of the Armed Forces Engineering Authority, Waziri said.
The project is scheduled to be completed after 211 days, he added.
On August 5, President Abdel Fattah El Sisi attended the inauguration of the waterway to be dug alongside the Suez Canal.
It is meant to add an extra lane to the Suez Canal, one of the world's most important thoroughfares for trade, in an attempt to increase the number of ships using it each day.
The Suez Canal, which allows ships to travel from Europe to Asia without passing through southern Africa, only provides for one-way traffic, with occasional room for ships to pass each other. The new lane would allow ships to travel in both directions at the same time.

arabstoday
arabstoday

Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

174m cubic meters dug at new suez canal project 174m cubic meters dug at new suez canal project

 



Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

174m cubic meters dug at new suez canal project 174m cubic meters dug at new suez canal project

 



GMT 14:55 2018 Saturday ,22 September

"President Abbas" Netanyahu always refused negotiations

GMT 04:49 2017 Wednesday ,13 September

So how do mega-storms get named, anyhow?

GMT 12:20 2017 Thursday ,24 August

The first World Xi'an Entrepreneurs Convention opens

GMT 12:58 2012 Wednesday ,20 June

The Hidden Power by Sameh Fawzy

GMT 06:33 2017 Tuesday ,05 December

English eyes on Griezmann for crunch Chelsea clash

GMT 07:30 2018 Wednesday ,26 September

Sudan-South Sudan Security Mechanism Meets

GMT 08:46 2017 Saturday ,12 August

Chinese President meets UN Secretary General
Arab Today, arab today
 
 Arab Today Facebook,arab today facebook  Arab Today Twitter,arab today twitter Arab Today Rss,arab today rss  Arab Today Youtube,arab today youtube  Arab Today Youtube,arab today youtube

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

arabstoday arabstoday arabstoday arabstoday
arabstoday arabstoday arabstoday
arabstoday
بناية النخيل - رأس النبع _ خلف السفارة الفرنسية _بيروت - لبنان
arabstoday, Arabstoday, Arabstoday