DEWA makes significant progress in Dh250m substation

Arab Today, arab today

Arab Today, arab today DEWA makes significant progress in Dh250m substation

Mohammed bin Rashid Al-Maktoum Solar Park
Dubai - Arab Today

Saeed Mohammed Al Tayer, MD and CEO of Dubai Electricity and Water Authority, DEWA, has confirmed that DEWA is progressing according to plan with the construction of the 400/132kV substation at the Mohammed bin Rashid Al Maktoum Solar Park.

"This supports the vision of Vice President and Prime Minister and Ruler of Dubai His Highness Sheikh Mohammed bin Rashid Al Maktoum, and the Dubai Plan 2021, to enhance Dubai's position as a global role model for achieving the highest standards in energy efficiency, renewable energy, creativity, innovation, and creating a sustainable future for generations to come," he said in a statement.

Al Tayer noted that DEWA is building a world-class energy infrastructure to meet all the development needs in the Emirate. Constructing the 400/132kV substation is part of DEWA's efforts to implement its strategy and ambitious plans according to the highest availability, reliability, and efficiency standards. This project includes supplying, installing, testing, and commissioning a 400/132kV substation with four 400kV cables. About 30% of the project's engineering work has been completed. The station is due to be completed by November 2016.

MD DEWA pointed out that the 400/132kV substation will connect the solar power generated from the 200MW second phase of the Mohammed bin Rashid Al Maktoum Solar Park, to DEWA's grid to supply Dubai with electricity. In the future, other phases of the Solar Park will be connected to the station to power new development projects in Dubai. There will be future expansions at the station. Another substation with the same capacity will be built to transmit the solar energy of the Solar Park, which is expected to reach 3,000MW by 2030.

The 400/132KV substation is being built at a cost of Dh250 million and has a 505 MVA transmission capacity. It is one of the projects of the Mohammed bin Rashid Al Maktoum Solar Park, which is one of the largest strategic Independent Power Producer, IPP, projects worldwide in renewable energy with a planned 1,000MW production capacity by 2020 and 3,000MW by 2030. The project supports the Dubai Integrated Energy Strategy 2030 developed by the Dubai Supreme Council of Energy to diversify the energy mix in the Emirate.

Solar energy will account for 7 percent of the total energy production by 2020 and 15 percent by 2030. The project, which occupies 4.5 square kilometres, will help achieve a reduction of approximately 400,000 tonnes of carbon emissions by 2020, and support the green initiatives and programmes implemented by the Government of Dubai to reduce carbon emissions.
Source: WAM

    

arabstoday
arabstoday

Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

dewa makes significant progress in dh250m substation dewa makes significant progress in dh250m substation

 



Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

dewa makes significant progress in dh250m substation dewa makes significant progress in dh250m substation

 



GMT 15:54 2017 Sunday ,16 April

PM: Britain uniting around Brexit

GMT 14:05 2017 Monday ,21 August

Ministry supports NGOs humanitarian mission

GMT 02:04 2017 Saturday ,09 September

11-year-old Saudi boy tortured by maternal uncles

GMT 09:18 2017 Friday ,17 November

NMC Health hits new highs in London

GMT 15:00 2017 Wednesday ,28 June

US House overwhelmingly backs NATO mutual defense

GMT 10:26 2017 Friday ,06 October

Mattel scraps plan for digital assistant for kids

GMT 03:32 2017 Saturday ,09 December

Global environment forum opens in Kenya

GMT 10:42 2017 Thursday ,26 October

Google and Cisco join forces in the cloud

GMT 23:10 2017 Thursday ,23 February

Le Pen aide charged in fake jobs scandal
Arab Today, arab today
 
 Arab Today Facebook,arab today facebook  Arab Today Twitter,arab today twitter Arab Today Rss,arab today rss  Arab Today Youtube,arab today youtube  Arab Today Youtube,arab today youtube

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

arabstoday arabstoday arabstoday arabstoday
arabstoday arabstoday arabstoday
arabstoday
بناية النخيل - رأس النبع _ خلف السفارة الفرنسية _بيروت - لبنان
arabstoday, Arabstoday, Arabstoday